|
THIS
EDITION  |
| |
A-400 doubles in size; move-in on schedule
By Monica Baires
Editor
After four months of demolition and almost six months
of remodeling and construction, A-400 has a tentative
completion scheduled for November.
“We are looking for substantial completion by
Nov.15,” construction manager Bill Bradford said.
“Then, a punch list will be done of all the things
that need to be adjusted and fixed. The contractor has
30 days to complete and fix this punch list.”
The project, which started in February, moved Student
Services across the street to the Holman building on
Walnut Hill.
As a result, the completion of the project will enable
students to obtain their services on campus during the
spring 2003 semester.
“Right now we are targeting Jan.21,” facilities
director John Watson said. “This date would work
out nicely because registration will have calmed down,
all the construction will be done, and people could
just unpack easily.”
During the construction and remodeling, A-400 was divided
into A-400 east (the new side) and A-400 west (the old
side), Bradford said.
“We’re right on schedule,” he said.
“In the A-400 west lobby area, the floor is being
prepared, the carpet and doors installed, and they are
finishing the final paint. I mean, it’s wrapping
up. Then, from the west, they are following up to finish
the east.”
Bradford gives the co-operation by the college and
the district credit for the project’s advance
in its schedule. Originally, the contract was extended
another 13 weeks, which would go into Jan. 10. But,
he said, they worked smart and hired more people.
“If you have a plan, and then you work out your
plan, everything goes right,” he said. “There
have been no safety issues, lost time or injuries up
there with the workers or the students.”
The A-400 project has added 20,000 sq. ft. to the building
and has remodeled 18,000 sq.ft. of pre-existing space.
Needless to say, the space of A-400 has doubled in size.
“We’ll be finishing the punch list by mid-December,”
Watson said. “Right now, we are determining furniture
needs and doing the ordering. It will probably arrive
for installation early in the new year and once the
furniture is placed, the project will be complete.”
Example with bullet to copy
|