Construction on campus continues
By Tom Ritchey
Editor
Waterproofing will force hill climb; MacArthur
roadway repair to begin The start of
the new semester also marks an increase in the
construction and waterproofing work across the
campus.
“I think we’re making great progress,”
said John Watson, director of facilities services
at North Lake College. With several projects in
the works, the construction work on campus will
be increasing throughout the semester.
North Lake College has been undergoing renovation
of the waterproofing in most of the buildings
on campus for a number of years. A new development,
found in early 2004 involving the rusting of metal
bolts that hold the brick façade to the
walls, has required the tearing down and rebuilding
of much of the brickwork on campus.
Watson said waterproofing work on the F and J
buildings by Chamberlin Waterproofing is making
progress. He said scaffolding will be erected
on the north and west faces of the F building
near the end of September. The sidewalk between
the A and F buildings will be blocked from public
use while waterproofing and construction continues
on the F building.
While the walk is inaccessible, Watson suggests
students walk up the adjacent hill and use the
entrance there. Information for students using
wheelchairs was unavailable at the time of the
interview.
Within the next six months, waterproofing work
should begin on P, H and K buildings.
Work on rebuilding the torn-up terrace above
the J building should start before October.
Repair work at the roadway entrance on Walnut
Hill. will begin soon, said Watson. The roadwork
will block off one lane of traffic at a time,
both entering and exiting the marquee entrance.
He said that the roadwork is “long overdue.”
Work on a project Watson calls Fire Alarm Rezoning
will soon start near the Gallery. Automatic fire
doors will be installed to create separations
between the various buildings in the main complex
in the event of a fire. The doors will be installed
at the junctions between the Gallery and the halls
connecting each of the surrounding buildings.
Once installed, Watson said that the doors will
automatically drop in case of fire and will take
some 8 to 10 seconds to drop.
Progress has been made concerning the slope failure
between the T building and the lake. On Oct. 3,
2001, the slope failed because of the combination
of underground water movement and rain. Watson
said that engineering studies of the slope are
essentially complete, and that the building slope
failure, “…has been a strange and
nasty challenge.”
Renovations inside the T building for the nursing
program will continue, he said. The nursing program
will be assigned a total of about 10,000 square
feet when construction is finished. There is currently
a temporary skills lab, a large classroom, and
a computer lab set up for nursing students. In
the former carpentry lab across the hall from
the completed nursing classrooms, Watson said
there will be a nursing suite that will serve
as a mock hospital area for the nursing students
to work in.
Watson said that he has received “…
just fantastic cooperation and tolerance”
from those on campus in regards to the construction
and waterproofing.
Construction and waterproofing work will continue
to increase in the next six months and even more
so beyond that, he added.
|